Market, Software
Development of Software Tool for Data Conversion from ENTSO-E PEMMDB to PLEXOS
Client: Energy Exemplar (United Kingdom)
Type: Software
Finishing date: December 2022
Team: Nebojsa Jovic - Project Manager, N. Georgijevic, O. Vukovic
Generation, Transmission, Renewable
Technical Solution for Connecting Switchyard 20/35kV Sastavci to 35kV Distribution Network
Client: Hydroenergy d.o.o. Gacko (B&H)
Type: Report
Finishing date: March 2023 (August 2023)
Team: Bosko Sijakovic - Project Manager, M. Stojanovic, S. Markovic - Consultant
Market, Policies
Organizational and Operational Support to Georgian Transmission System Operator (GSE)
Client: Fichtner Management Consulting AG (Germany), European Union, GSE (Georgia)
Type: Other
Finishing date: April 2023
Team: Slobodan Markovic, Djordje Dobrijevic
Generation, Transmission
Small Signal Stability Analyses for Barakah Nuclear Power Plant (BNPP) – Unit 3
Client: Mott MacDonald (UAE), TRANSCO (UAE)
Type: Report
Finishing date: January 2023
Team: Predrag Miksa - Project Team Leader, N. Jovic
Transmission, Software
Provision of License of the TNA v2.4 Software with Training, Maintenance and Support for the Independent Power Transmission Operator
Client: IPTO - Independent Power Transmission Operator (Greece)
Type: Software
Finishing date: March 2023
Team: Bogdan Lutovac – Project Manager, B. Brdjanin
Software
NOSBIH TNA Software Maintenance 2022
Client: NOS BiH (Bosnia and Herzegovina)
Type: Software
Finishing date: January 2023
Team: Boris Brdjanin – Project Manager, B. Lutovac
Transmission
Study of Connection of Baltic countries to ENTSO-E Continental Europe
Client: JCS Elektromreza Srbije (Serbia), Baltic TSOs, European funds
Type: Study
Finishing date: November 2022 (January 2023)
Team: Consortium IMP Automatika (Serbia) - EKC; EKC team: Milan Ivanovic - Project Manager, Dj. Dobrijevic, N. Jovic - Consultant
Generation, Market, Policies
Armenia Energy Storage Program: Energy Modeling and Economic/Financial Analyses
Client: The World Bank
Type: Study
Finishing date: December 2022 (March 2023)
Team: Dragana Orlic – Project Manager, D. Vlaisavljevic, M. Kostic, N. Miljanic
Generation, Transmission, Market
Consultancy Services to Perform Adequacy Studies within the TEASIMED
Client: Mediterranean Transmission System Operators – MED-TSO (Italy)
Type: Project
Finishing date: December 2022 (June 2023)
Team: Dragana Orlic – Project Manager, D. Vlaisavljevic, I. Mihajlovic Vlaisavljevic, B. Lekovic, M. Kostic
Transmission
Flexible Alternating Current Transmission System (FACTS) for Reactive Power Compensation for the Kazakhstan Electricity Grid Operating Center (KEGOC)
Client: USEA, USAID
Type: Study
Finishing date: December 2022
Team: Milan Stojanovic – Project Manager, M. Ivanovic, N. Georgijevic, B. Brdjanin