System Analyses Needed for Study of Connection of Revitalized unit of TPP (367MVA) to Serbian Transmission Grid

Serbia
System Analyses Needed for Study of Connection of Revitalized unit of TPP (367MVA) to Serbian Transmission Grid

client: Elektromreza Srbije AD (Serbia)

type: Study

finishing date: December 2017

team: Djordje Dobrijevic - Project Manager; B. Sijakovic, Nebojsa Jovic - Consultant

The main goal of this study is to provide to TSO all necessary information for study on connection of the revitalized unit of TPP, installed power of 367MVA, after first phase of revitalization in which only turbine should be replaced. The unit is connected to 220kV voltage level of the electric transmission grid of Serbia. Following design studies have been provided: checking of voltage-reactive capability and selection of proper step-up transformer ratio; load flow studies including contingency analysis; fault calculations; static stability studies and transient stability studies including CCT calculation; mid-term stability analysis; checking of requirements defined in national grid code.

Type of services provided:

  • Load flow analysis
  • Contingency analysis
  • Short-circuit calculation
  • Stability analysis
  • Checking of voltage-reactive capability
  • Selection of proper step-up transformer ratio
  • Checking fault-ride-through requirements
  • Checking Grid Code requirements