Grid Compliance Testing of WPP Krnovo

Montenegro

client: CGES a.d. (Montenegro)

type: Technical Support

finishing date: July 2017

team: Nebojsa Jovic – Project Manager, M. Vukovic – Consultant, M. Stojanovic, M. Ivanovic

The objective of this project is to support CGES, as Transmission System Operator, in the processes of revision of testing protocols, conduction of on-site tests as well as revision of grid compliance testing report. This support comprises the following activities:

  • Revision of grid compliance testing protocol for WPP Krnovo
  • Support during conduction of on-site tests
    • Active power control
      • Test of active power control
      • Test of frequency response
      • Test of active power ramping rates
    • Voltage control
      • Test of automatic voltage control mode
      • Test of automatic reactive power control model 
      • Test of automatic power factor control mode
      • Test of reactive power capabilities
    • Low Voltage Ride Through
      • Test of fault ride through capability
    • Power Quality
      • Test of influence of WPP to power quality parameters
    • Test of signals, communication and control
      • Test of communication signals between WPP and CGES
    • Validation of simulation model
  • Revision of grid compliance testing report based on which the final operational notification for WPP Krnovo is issued

Type of services provided:

  • Revision of testing protocol
  • On-site tests
    • Active power control
    • Voltage control
    • Fault-ride Through Capability
    • Power Quality
    • Signals, communication and control
  • Revision of grid compliance testing report